Network Tasman delegate design pricing and construction to our local Authorised Line Contractors (ALC). The ALC will prepare a reticulation design for your new subdivision, new line extension, alteration or other development.
Design and Pricing
Start by contacting an ALC of your choice to discuss your power requirements.
They will submit their design to us for approval, and once approval is given they will provide you with a free competitive quote for the new reticulation works.
The Connection of New Loads Policy determines what levies or contributions are payable by the developer to us, or alternatively, what if any, contribution we will pay to the developer.
Levies are calculated by powerline distances and requested capacity in kVA or number of lots.
Contributions by us are calculated on the number of lots, residential and/or commercial, and HV assets that will be vested to Network Tasman.
Items such as HV switchgear and distribution transformers are normally provided free of charge. However, you will be required to arrange delivery of these to your site.
Assets that have been altered/upgraded by other developers previously may incur a reappointment cost payable prior to use.
Kia ora Tapawera, St Arnaud, Kikiwa and surrounding areas. We have three outages coming up for your supplying substation on Sundays over March/April to allow us to install new equipment at site. Unfortunately, this will mean having to turn the power off while we do the work. Apologies in advance for the inconvenience, and we'll look to put some imagery up during each of these days to show you what we're doing. A reminder that if you are impacted by this outage you will be notified by your retailer or Network Tasman directly. (As per notice below, some people will be covered by back up generation being supplied by Network Tasman). ... See MoreSee Less